Q. What is the status of the Goldschleger Library Renovation Project?

Answer

The Goldschleger Library is currently being renovated. 

The following dates are approximate and may change during the project. 

Dec 2018 Jan 2019 - Library was emptied 

Jan 2019 – Oct 2019 - Renovation in progress

  • Goldschleger Building is be closed and undergoing renovation
  • The Weitz Building, near Charlie’s Restaurant houses books, quiet and group study rooms, and Library staff 
  • All print journals are in storage and accessible to patrons by request 

Oct 2019 – Feb 2020

  • Goldschleger Building is expected to reopen with semi-quiet study desks and a large social zone 
  • Library books and staff will remain in the Weitz Building until further notice

Thank you for your patience. 